C Keathley Construction & Design Corp A2017-155 CO#1Project No Project: CITY OF CHINO HILLS CHANGE ORDER NO. 8/29/2017 120058 Hickory Creek Headwall Contractor: C Keathley Construction 703 S Gifford Ave Suite 207 San Bernardino, CA 92408 Contract No, P.O. No. Account No. A2017-155 170696 001-8121-888-8040 Distribution: Original to City Clerk Contractor Purchasing Department DESCRIPTION: Current Change Order 44.8% Overexcavate, place aggregate, and install sump pump in order to dewater the work area due to excessive seepage $ 6,450.00 Amount $ 6,450.00 Contract Time Adjustment, Add - 10 - Working Days. ORIGINAL CONTRACT AMOUNT $ 14,400.00 Change Orders to Date: Add Deduct Change Orders to Date Adjusted Contract Amount Change Orde 1 Add $ 6,450.00 Deduct Net Change Order Total Change Orders RECOMMENDED APPROVAL BY: NADEEM MAJAJ, P.E.'r PUBLIC WORKS DIRECTOR APPROVAL BY: 0.0% c� $ 14,400.00 KONRADT BARTLAM CITY MANAGER DATE: g;�� /7 — 44 R% $ 6,450.00 AMENDED CONTRACT AMOUNT $ 20,850.00 ACCEPTED BY: i C Keathley Construction