Jeremy Harris Construction A2015-203 - CO2 CITY OF CHINO HILLS
CHANGE ORDER NO. 2
December 10,2015
Project No. 120049 Contract No. A2015-203
Project: Lower Los Serranos Skate Park P.O.No. 160517
Channel Outlet and Box Culvert Account No. 181218883190
Sediment Removal Project
Contractor: Jeremy Harris Construction Inc. Distribution:
19466 Lurin Ave. Original to City Clerk
Riverside,CA 92508 Contractor
Purchasing
Department
DESCRIPTION: Current Change Order
Additions
1 Reduce retrention form 10%to 5%in accordance with Project Specifications
and Standard Specification for Public Work(Greenbook) provisions.
Total Value of Change Order#2 $0
Contract Time Adjustment,Add/Subtract- 0 -Working Days.
ORIGINAL CONTRACT AMOUNT $ 225,645.00 CITY OF CHINO HILLS w
Authorized this the 15"--'—day of
Change Orders to Date: 1 n pecember , 2015.
Add $ 44,461.00
Deduct $ 35,880.00 $ 8,581.00
KONRADT BARTLAM
Change Orders to Date 3.8% CITY MANAGER
Adjusted Contract Amount $ 234,226.00
APPROVED BY:
Change Order No. 2 Ii --
Add
Deduct NADEEM MKJAJ
PUBLIC WORKS DIRECTOR
Net Change Order $ -
Total Change Orders 3.8% ACCEPTED BY:
AMENDED CONTRACT AMOUNT $ 234,226.00
n
REMY HA IS CONSTRUCTION